| |
EQUITABLE
ADJUSTMENTS
GET
WHAT YOU ARE OWED
By R. Chris Puffer
The equitable adjustment process can be very frustrating. Even
when the Government acknowledges liability, it often disagrees with
the contractor’s assessment of extra costs or time and offers significantly
less than the amount requested.
This issue describes the various approaches to getting all that
you are owed in your next equitable adjustment. Additionally, it
provides practical tips that will help increase the likelihood of
a favorable settlement. In our next issue, we will cover the "total
cost" and "modified total cost" methods of proving how much you
are owed.
When trying to obtain equitable adjustments associated
with Government-caused changes, it is important to remember that
the amount of the adjustment (the "quantum"), whether it is for
money or contract time, is not the first thing the contractor should
establish Initially, a contractor must establish (1) liability on
the part of the Government and (2) the causal link between the Government’s
conduct and the contractor’s injury. Frequently, the Government’s
hesitancy to agree on quantum is because it either doesn’t completely
agree on the liability issue or it is not convinced that it’s conduct
actually caused the type of additional expense asserted by the contractor.
Do an Impact Analysis
The causation issue is often a major problem area for contractors,
particularly when they are concerned about maintaining a good customer
relationship. Contractors will often minimize the impact of Government
changes and then later find themselves "upside down," where the
revenues received are less than their costs of performance. Consequently,
contractors should perform a careful impact analysis of the true
cost of a change, both from a direct cost and indirect cost standpoint.
When a contractor understands the true impact, it can make an informed
business decision about whether to push for an adjustment.
Segregate Actual Costs If Possible
The method preferred by contracting officers, auditors and judges
to prove the amount of an equitable adjustment is the actual cost
method, in which the contractor provides specific documentation
of the actual, and reasonable, expenses caused by the Government’s
conduct. In many contracts, the Government includes the "Change
Order Accounting" clause, which requires that a contractor segregate
the costs of performing the changed work. While this clause contains
no penalty for not complying, the failure of a contractor to do
so when it reasonably could have segregated cost only serves to
complicate and delay settlement. Moreover, actual segregated cost
records eliminate most of the objections that can be raised by a
Government auditor, which will permit the contracting officer to
proceed with a quicker resolution.
In a recent case, Doninger Metal Products v. U.S., 50 Fed. Cl. 110
(Fed. Cl., Jul. 31, 2001), a contractor, described by its president
as a "ma and pa type," attempted to prove actual costs using summaries
where the source documents were not available. Under the circumstances,
the court refused to accept its summaries as adequate proof of actual
costs. Consequently, the contractor’s equitable adjustment was limited
to the much lower amount calculated by the contracting officer.
Estimates Have to be Fully Supported
When actual costs are difficult to establish, a contractor must
resort to an estimating method that quantifies all labor, material
and indirect costs. Even though courts have consistently permitted
estimates ("equitable adjustments do not have to be established
with absolute exactness or mathematical precision"), they do nonetheless
have to provide a reasonable basis for computation.
When using estimates, contractors must overcome the tendency to
say, "they’re just estimates" and not be diligent in their preparation.
In fact, contractors should use as much rigor in preparing estimates
as they would in compiling and reporting actual costs. All supporting
documents, the factual basis of all assumptions and the logic of
the computation must be clearly laid out. If the estimate is not
completely supported, the Government’s auditor will probably write
a negative audit report or, at a minimum, significantly discount
the amount requested. Such a report will seriously hamper the ability
of the contracting officer to settle the matter (even if he or she
agrees that the contractor is entitled to an adjustment). Without
a settlement, a contractor will be forced to resort to litigation.
If a contractor proceeds with litigation and presents its estimate
to a judge, the judge may make an award using a "jury verdict" approach,
which is simply the result of the judge weighing the parties’ conflicting
views as to the validity of the contractor’s estimates. However,
it is important to remember that, even though judges can use the
"jury verdict" approach, a contractor should not be lulled into
believing that its standard of proof is somehow less or that it
"will always get something." In fact, judges will only resort to
using jury verdicts when (1) there is clear proof that an injury
occurred, (2) there is no more reliable method for computing the
amount of the adjustment and (3) the evidence is sufficient for
the judge to make a fair and reasonable approximation of the damages.
In conclusion, a contractor should take great care in preparing and
submitting a request for an equitable adjustment, whether it is based
on actual costs or estimates of cost. The amount negotiated with the
contracting officer or awarded by a judge will be directly related
to the soundness of the approach the contractor uses.
|